| $3,000 DIY Manual Pad |
| Written by Peter Whitley |
| Sunday, 02 May 2010 17:04 |
|
Here are step-by-step instructions on how to build a manual pad for under $3,000. This project was demonstrated in Tacoma, Washington in April, 2010 and took three days of work over a two-week span. Step 1: FundingThe local skatepark committee approached the neighborhood council with a proposal to introduce a new skateboarding structure at an existing skatepark. Once a year the council is provided foundation funds to award community programs. The improvement required a letter of concurrence from the Parks Department. This document demonstrated the Parks' support and approval of the construction. Given the skatepark committee's long-time involvement with area skateparks, there were few questions or concerns about their ability to implement the plan on schedule and to professional standards. The skatepark committee applied for the grant and prepared to present the project in person at the appropriate meeting. A few key points were covered as evidence that this project was a win-win for the whole community. Namely, the value and importance of the skatepark to the neighborhood youth was emphasized. The age—16 years—of the skatepark without any kind of modification was also brought up. Finally, the group's commitment to ensuring compelling, sustainable, and safe terrain was outlined. The proposal was awarded the full sum of its request. Step 2: Planning
Reference photos and measurements were taken of the area slated for construction. Step 3: MaterialsA punchlist of services, materials and tools was prepared so that nothing would be overlooked. Luckily a large, well-stocked hardware store was less than a mile away from the site so overlooked items weren't going to present a scheduling crisis. At this point the dimensions and design are finalized. TOOLS Extension cords RENT
Generator Step 4: Order ServicesThree services were required for this project: Concrete cutting was necessary as the manual pad creation was combined with a quick refurbishment of another ledge in the skatepark that was worn out. The intent here was to cut out the retired edge of the ledge and replace the missing notch with granite. Once the volume of concrete was known, the committee scheduled the concrete delivery. Two challenges arose with the concrete delivery. First, the committee wanted a weekend delivery. This is atypical for concrete supply companies as most of their clients are large construction firms following an ordinary work week. Second, the volume of concrete was relatively small. Most concrete companies would see little reason to be flexible or accommodating for such a small project. After some research a company was found that could perfom on-site mixing to whatever volume was required and was willing to deliver on a Saturday. For this project a 6-bag mix was requested.
With all of the services ordered the schedule was now set and could not be easily changed. Two weeks prior: Order granite Step 5: Concrete CuttingPrior to the concrete cutter arriving on site, a committee member measured and marked the portion of the ledge that was to be removed. Given that the granite brick would be 6 x 3 inches, the notch to hold it should be 6.5 x 3.5 inches. The additional half-inch will allow for a bed of grout that the granite will rest on.
The unwanted concrete was left resting in place to discourage tampering. The concrete cutting service was paid at the conclusion of their service on site. The concrete service will supply their own water and generator if you indicate that they are not available on site.
Step 6: Create and Install Forms
The "notch" represents the area that will later be occupied by the granite bricks. The concrete will be poured to the top of the form and smoothed off.
Holes are drilled into the slab and rebar anchors are hammered into them. The anchors are bent 90-degrees so that longer pieces can be wired to them. This cage will provide strength to the manual pad and prevent cracking and breaking due to subtle shifts in the slab.
Rebar posts were hammered into drilled holes outside of the form to provide additional support. The blocks of concrete under the cage are the pieces removed from the concrete cutting service. These bits will slightly reduce the amount of concrete needed to fill the form. The insides of the form are lightly smeared with oil to allow them to break away from the concrete when they are removed.
Step 7: Concrete Pour
The concrete is mixed in the truck with calcium to make it set quickly. Shovels are used to push the concrete into all of the recesses in the form. The sides of the form were tapped continuously with a hammer to knock out any bubbles as the form is filled.
After the mag float is used to smooth the surface of the concrete, the concrete is given a few minutes to firm up.
Note the tarp in the background to protect the wet concrete from rain. Water not only slows drying time but can damage the surface of the concrete. Tarps were used to keep the wet concrete away from the rain.
Step 8: Granite and Grout
Shims are used to create spacers under the granite.
The grout is glopped against the back corner of the notch. The grout is placed around and over the spacers. When enough grout is laid in the notch to completely fill the space beneath the granit block, the granite is lifted and set into place. The granite is then slightly moved and adjusted on the bed of grout until the top is aligned with the top of the manual pad. Excess grout should ooze out from the space beneath the block.
It is not critical to create a beautiful grout joint. The priority should be to ensure that grout is completely behind and underneath the granite block. Note the granite awaiting grout on the other side of the ledge.
Fingers, plastic knives and all sorts of devices are then used to finish the grout joints. They should be flush with the surfaces of the concrete and granite.
Step 9: Wrapping Up
The water served as a good indicator for when the new manual pad was ready to try out. When the water was evaporated the new structure could be skated. The skatepark regulars played a game of SKATE to determine who got to take the inaugural run.
Expense BreakdownGenerator Rental: $55.00 TOTAL: $2,906.86 Volunteer Hours: 50 |
| Last Updated on Sunday, 02 May 2010 19:48 |


Granite fabrication was simply a matter of sketching out the desired forms and sending it to the quarry and stone fabrication company. Because the committee had experience with replacing ledges with granite bricks, little research was required to find a source or determine how the information should be conveyed. A simple PDF with a diagram of the desired pieces was created.